Project overview

We’re building approximately 750 metres of new sewer pipes under Melbourne’s CBD and Docklands, to double the capacity of the sewer. The new pipeline will be installed under Flinders Lane, Spencer Street, Siddeley Street and Wurundjeri Way.

This project will be delivered by Aqua Metro for Greater Western Water.

We’re committed to letting local communities know about our works. If you live in the area, we’ll send you a letter with more information before we start construction. As the project continues, we’ll keep you updated.

Project update

This is a notice under section 175 of the Water Act 1989 (Vic).

Due to population growth Greater Western Water intends to build a new sewer on Siddeley Street, Flinders Lane, Spencer Street and Wurundjeri way to improve the network and ensure reliable sewer services for the local community.

Construction activities would affect residents and businesses on Flinders Lane, Spencer Street, Flinders Street, Siddeley Street and Wurundjeri Way.

If you wish to make a submission about the proposed construction, you can send your submission to Greater Western Water either by:

Mail: Locked Bag 350, Sunshine VIC 3020

Email: engagement@gww.com.au

Online: gww.com.au/contact-us

Submissions must be received no later than close of business Friday 19 December 2025.

If no submissions are received, Greater Western Water intends to carry out the construction works from Monday 6 January 2026.

For general enquiries regarding this notice or the proposed works please connect with us via gww.com.au/contact-us or call 13 44 99 and we will get back to you as soon as possible during business hours Monday to Friday.

Construction of the new sewer

Major construction on the new sewer is expected to start in early 2026. If you live near our works, we will update you and provide more specific details before our construction starts.

Location of sewer construction

The line on the map below shows where we will install the underground sewer pipe. The pins show the location of our construction sites.

Current and upcoming works

We are currently completing works to prepare for construction of the new sewer.

Relocating other underground utilities

Before we start construction on the new sewer, we need to move some other underground utilities. This work will be at multiple locations starting from late October 2025.

Other GWW works

To prepare for this project, GWW is completing some essential maintenance on the existing sewer. This work is being carried out by our Delivery Partner Rangedale.

The locations of our maintenance work is shown below, with more information about expected impacts at each site. You may also see our workers accessing the sewer via maintenance holes at various locations along Flinders Street.

If you have questions or feedback on these maintenance activities, please contact GWW:

  • Email: engagement@gww.com.au
  • Phone: 13 44 99