Key information

  • Timing: From Sunday 19 October for 1 to 2 weeks.
  • Construction hours: 7pm to 6am, Sunday to Thursday

What to expect during this work

  • There will be some noise from generators and construction vehicles. We will aim to schedule noisier work early in the evening where we can.
  • There will be a temporary footpath closure at our worksite, and some parking bays will be closed during construction hours.
  • There will be traffic management in place to help pedestrians and vehicles continue to move safely around the area.
  • Outside of construction hours, the parking and footpaths will reopen to traffic.

Why does this work need to be completed at night?

These works require access to a live sewer, which means we need to work when sewer flows are low during the night.

Location of works

Work is happening in the red area shown below.